This documents related to 2019-09, the Eclipse Foundation's multi-project Simultaneous Release of September 2019.
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release |
Date |
Span |
Due dates |
Notes |
---|---|---|---|---|
2019-09 M1 |
Friday, July 19, 2019 |
07/12 to 07/19 |
|
3 weeks from 2019-06 GA |
2019-09 M2 |
Friday, August 9, 2019 |
08/02 to 08/9 |
3 weeks from M1 |
|
2019-09 M3 |
Friday, August 30, 2019 |
08/23 to 08/30 |
|
3 weeks from M2 |
2019-09 RC1 |
Friday, September 6, 2019 |
08/30 to 09/06 |
|
1 week from M3 |
2019-09 RC2 |
Friday, September 13, 2019 |
09/06 to 09/13 |
1 week from RC1 |
|
Quiet period |
09/13 to 09/17 |
No builds during "quiet period". It is assumed all code is done by the end of RC2. |
||
2019-09 GA |
Wednesday, September 18, 2019 |
|
5 days from RC2 |