This documents related to 2020-09, the Eclipse Foundation's multi-project Simultaneous Release of September 2020.
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release |
Date |
Span |
Due dates |
Notes |
---|---|---|---|---|
2020-09 M1 |
Friday, July 17, 2020 |
07/10 to 07/17 |
|
3 weeks from 2020-06 GA |
2020-09 M2 |
Friday, August 7, 2020 |
07/31 to 08/07 |
3 weeks from M1 |
|
2020-09 M3 |
Friday, August 28, 2020 |
08/21 to 08/28 |
|
3 weeks from M2 |
2020-09 RC1 |
Friday, September 4, 2020 |
08/28 to 09/04 |
|
1 week from M3 |
2020-09 RC2 |
Friday, September 11, 2020 |
09/04 to 09/11 |
1 week from RC1 |
|
Quiet period |
09/11 to 09/15 |
No builds during "quiet period". It is assumed all code is done by the end of RC2. |
||
2020-09 GA |
Wednesday, September 16 2020 |
|
5 days from RC2 |