This documents related to 2022-06, the Eclipse Foundation's multi-project Simultaneous Release of June 2022.
- Simultaneous Release Requirements (aka must-dos)
- Simultaneous Release Plan - Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release |
Date |
Span |
Due dates |
Notes |
---|---|---|---|---|
2022-06 M1 |
Friday, April 15, 2022 |
04/08 to 04/15 |
|
|
2022-06 M2 |
Friday, May 6, 2022 |
04/29 to 05/06 |
3 weeks from M1 |
|
2022-06 M3 |
Friday, May 27, 2022 |
05/20 to 05/27 |
|
3 weeks from M2 |
2022-06 RC1 |
Friday, June 3, 2022 |
05/27 to 06/03 |
|
1 week from M3 |
2022-06 RC2 |
Friday, June 10, 2022 |
06/03 to 06/10 |
1 week from RC1 |
|
Quiet period |
06/10 to 06/14 |
No builds during "quiet period". It is assumed all code is done by the end of RC2. |
||
2022-06 GA |
Wednesday, June 15, 2022 |
|
5 days from RC2 |