This documents related to 2024-06, the Eclipse Foundation's multi-project Simultaneous Release of June 2024.
-
Simultaneous Release Requirements (aka must-dos)
-
Simultaneous Release Plan Information that stays the same for each release, like requirements for participation, communication channels, etc.
Release | Date | Span | Due dates | Notes |
---|---|---|---|---|
2024-06 M1 | Friday, April 12, 2024 | 04/05 to 04/12 | 3 weeks from 2024-03 GA | |
2024-06 M2 | Friday, May 3, 2024 | 04/26 to 05/03 | 3 weeks from M1 | |
2024-06 M3 | Friday, May 24, 2024 | 05/17 to 05/24 | 3 weeks from M2 | |
2024-06 RC1 | Friday, May 31, 2024 | 05/24 to 05/31 | 1 week from M3 | |
2024-06 RC2 | Friday, June 7, 2024 | 05/31 to 06/07 | 1 week from RC1 | |
Quiet period | 06/07 to 06/11 | No builds during "quiet period". It is assumed all code is done by the end of RC2. | ||
2024-06 GA | Wednesday, June 12, 2024 | Release reviews conclude on this date | 5 days from RC2 |