It would be cool if we can configure our Gantt chart so that the dates are inclusive. For example if there is a task from June 1st to June 3rd I can write 2019-06-01, 2019-06-03. Currently the ending date is exclusive, so I have to write 2019-06-01, 2019-06-04 which is counter-intuitive.
It can be either a switch in JavaScript API, or some command in the diagram definition (similar to dateFormat and title).
The text was updated successfully, but these errors were encountered:
This is a feature request.
It would be cool if we can configure our Gantt chart so that the dates are inclusive. For example if there is a task from June 1st to June 3rd I can write
2019-06-01, 2019-06-03
. Currently the ending date is exclusive, so I have to write2019-06-01, 2019-06-04
which is counter-intuitive.It can be either a switch in JavaScript API, or some command in the diagram definition (similar to
dateFormat
andtitle
).The text was updated successfully, but these errors were encountered: