Hi Will there be any downtime during a new apply / replace on the latest version during an upgrade? |
Beta Was this translation helpful? Give feedback.
Answered by
zachaller
Nov 4, 2022
Replies: 1 comment
-
There should not be downtime any current reconciliations would pause and continue when the new controller comes online. |
Beta Was this translation helpful? Give feedback.
0 replies
Answer selected by
zachaller
Sign up for free
to join this conversation on GitHub.
Already have an account?
Sign in to comment
There should not be downtime any current reconciliations would pause and continue when the new controller comes online.